More than two years since construction started, toilets remain incomplete in Free State village

Published by
By GroundUp

In April 2019 the Mangaung Metropolitan Municipality appointed Makomota Stone to build 390 toilets in Moroka extension 27 and install water connections in Ratau, Thaba ’Nchu.

The contract was worth nearly R23 million and work started in May 2019.

Contractor struggled with cash flow

But progress was slow, according to municipal spokesperson Qondile Khedama. He said the contractor struggled with cash flow.

Advertisement

By May 2021, the municipality had initiated a termination of contract, finalised on 15 October 2021. It had paid Makomota Stone R5.7-million. Khedama said that when the contractor left, sewer mains were 90% completed, water mains 94% and toilet structures only 64%. [It’s unclear how these percentages are calculated – editor].

A year since the termination and over two years since construction began, the villagers sit without water or new toilets.

Trenches had been excavated and water pipes laid, but there are no taps and there is no water supply. Residents depend on water tanks. Last week, they said the tanks hadn’t been filled for 12 days. Water is also fetched from streams.

Advertisement

Only the walls of about 275 toilets have been built. Some people use zinc sheet-enclosed pit toilets they’ve dug themselves.

People resort to plastic bags and buckets

Villagers in Thaba ’Nchu ward 39 use these zinc toilets they built themselves.

Lerato Poonyane, ward 39 community leader, said people use buckets and plastic bags in which to relieve themselves at night. She said children can be seen relieving themselves on the streets during the day. It has become normal as going into the bush is not considered safe.

Resident Tailor Mtemeki said they received their plots from the municipality in 2017. There were no services for the nearly 300 sites, but in 2018 they were promised water and sanitation.

Advertisement

“We got so excited when the contractors packed toilet material at each household, while the digging of water pipes in the streets was proceeding … Little did we know,” said Mtemeki.

Bricklayer Kgosiame Sebotsa worked for Makomota Stone. He said the workers sometimes they waited two months for payment. He said they were never informed why the contractor left. They turned up one day to find the site deserted.

GroundUp tried several numbers listed for Makomoto Stone, but they were all defunct.

Advertisement

Khedama said the previous ward councillor, Betty Cezula, called several meetings to explain that the contract was terminated.

He said they have since appointed a consultant, compiled a tender document for the outstanding work, and a tender will be advertised.

This article originally appeared on GroundUp and was republished with permission.
Read the original article here.

Advertisement

NOW READ: We want more toilets and better access to water, say Centurion shack dwellers

For more news your way

Download our app and read this and other great stories on the move. Available for Android and iOS.

Published by
By GroundUp
Read more on these topics: Mangaungtoilets