The probe into the tragic Grayston bridge collapse continues

The inquiry was instituted by the department of labour following the collapse of the M1 pedestrian and cyclist bridge in 2015.


The M1 Grayston Bridge inquiry, which was postponed in August 2016, will resume in Pretoria on September 26.

The event will take place at the Pretoria Labour Centre offices, Concillium Building at the corner of Nana Sita and Thabo Sehume. The sitting will start at 9am.

The inquiry, which is being held in terms of Section 32 of the Occupation, Health and Safety Act, was instituted by the department following the collapse of the M1 pedestrian and cyclist bridge on October 14, 2015, resulting in the deaths of two people and injuries to 19 others.

The inquiry seeks to establish the cause of the accident. It is being conducted by Lennie Samuel after being instituted by the department of labour’s chief inspector, Tibor Szana.

Stakeholders include the Johannesburg municipality as the client, Johannesburg Development Agency (JDA) as the agent, Murray and Roberts Infrastructure (MR) as the principal contractor appointed by JDA and Form Scaff as a contractor appointed by Murray and Roberts.

Already a number of expert witnesses have been called, among them Roelf JM, an expert witness representing Murray and Roberts, Richard Beneke, an expert witness representing Murray and Roberts, Ric Snowden, an expert witness representing Murray and Roberts, Stefanus Francois van Zyl, an expert witness representing Murray and Roberts, and Garry Farrow, an expert witness of Form Scaff.

It is expected that more witnesses will be called and that the inquiry will conclude its business at the end of September next year.

http:////

For more news your way, follow The Citizen on Facebook and Twitter.

Read more on these topics

Department of Labour

For more news your way

Download our app and read this and other great stories on the move. Available for Android and iOS.