Load Shedding

Load shedding to alternate between stage 4 and 5 this week

Eskom has announced that it will ramp up load shedding to stage 4 from 4pm on Sunday.

Load shedding

The struggling power utility said stage 4 rolling power cuts will be implemented until 4pm on Monday. After that, stage 5 load shedding will be implemented until 5am on Tuesday.

ALSO READ: Providing electricity not government’s job argues Ramaphosa

Advertisement

“The pattern of stage 4 load shedding from 05:00 to 16:00 and stage 5 load shedding from 16:00 to 05:00 will be repeated until further notice,” Eskom said in a statement.

This comes after South Africans got a slight reprieve from the crippling power cuts that were downgraded to stage 1 earlier on Sunday.

Generating units

Eskom spokesperson Daphne Mokwena said over the past 24 hours, a generating unit at Arnot Power Station was successfully returned to service.

Advertisement

During the same period, a generating unit each at Kriel, Medupi, and Tutuka power stations were taken offline for repairs.

“The return to service of a generating unit each at Duvha, Medupi, Tutuka, and two units at Hendrina power stations are delayed.

“The repairs to the damaged towers from Cahora Bassa in Mozambique are continuing and are anticipated to be completed by early next week.”

Advertisement

Breakdowns increased to 17 008MW of generating capacity, while 4 600MW of generating capacity is out of service for planned maintenance.

NOW READ:  Load shedding, uncaring clinic staff cut mother’s life short

For more news your way

Download our app and read this and other great stories on the move. Available for Android and iOS.

Published by
By Citizen Reporter
Read more on these topics: EskomRolling blackouts