Load Shedding

Load shedding ‘likely’ until December, says Eskom

Published by
By Moneyweb

Wet coal aside, Eskom’s immediate outlook for its available generation capacity is much improved from a month ago.

At that time, its three-month outlook published in its weekly system status reports indicated that until mid-April, it would “definitely” be between 1000 megawatts (MW) and 2000MW short to meet its reserve margin and “possibly demand” for six of the 13 weeks.

This picture has steadily improved from early January until now.

Advertisement

In the most recent update, published at the end of last week, it sees risk in just one week (specifically next week) where it is likely to be between 1000MW and 2000MW short to meet demand (including its operating reserve).

For seven of the next 11 weeks, it may be less than 1000MW short to “meet reserves”.

Source: Moneyweb, using data from Eskom Weekly System Status Report

There are an awful lot of assumptions here, chiefly that 12,000MW of capacity will be offline due to breakdowns (added to this is 2200MW required for its operating reserve to get to the 14,200MW “planned risk level”).

Advertisement

ALSO READ: Eskom patting itself on the back for delivering on its mandate

If there is no sudden spike in breakdowns, the picture looks significantly more positive than it did at the start of the year.

Even if there is a forecasted shortfall, Eskom is typically able to meet this peak demand with its peaking power plants – either open cycle gas turbines (OCGTs) and pumped storage schemes, or OCGTs operated by independent power producers (IPPs).

Advertisement

The utility is usually also able to ride out breakdowns of the odd unit (generally an impact of 500MW to 800MW) by using this peaking power as baseload power.

However, it’s when a number of units trip or break down simultaneously that it is forced to implement load shedding, as these outages typically total 2000MW (or higher).

The generation outlook for situations when there is this spike in breakdowns does not improve until the end of March.

Advertisement

ALSO READ: Eskom blames rain for load shedding rather than its failing power systems

For context, Eskom said on Tuesday that “14,375MW of capacity is unavailable due to breakdowns and delays”.

This necessitated stage 2 load shedding overnight as it needed to replenish its emergency generation reserves (chiefly its pumped storage schemes which it is using for baseload power, given the high level of breakdowns).

Advertisement
Source: Moneyweb, using data from Eskom Weekly System Status Report

From its near-term outlook, the overall improvement has not come at the expense of a reduced forecast in demand, nor at the expense of the level of planned maintenance.

This suggests it could only be as a result of steadily improving generating capacity.

Eskom has also made a further material change to its assumptions from April: that unplanned outages would be 11,000MW, not the historical 12,000MW level that has been used for a number of years.

Kendal Unit 5, which can produce 640MW and has been on a long-term forced outage, is the only possible explanation for this as it returns to service in April.

It is unclear whether Eskom is continuing to plan using a risk level of 14,200MW in outages (or a likely risk scenario of 16,200MW), but this is not likely as it requires only 2200MW as operating reserve.

In its system status report from last week, Eskom also for the first time published a forecast for the next year. It typically only shares a three-month view.

ALSO READ: Eskom ‘in trouble’ as it burns expensive diesel to keep lights on

Its outlook shows that it expects a small shortfall to meet reserves in most weeks for the remainder of the year. When (or if) breakdowns do spike, load shedding is very likely (red) until April when that Kendal unit returns to service (Koeberg Unit 1 returns to service in May).

Beyond that, the outlook does not look encouraging. Eskom’s ability to juggle breakdowns across an ageing fleet will determine just how much load shedding we endure until December.

Source: Moneyweb, using data from Eskom Weekly System Status Report

Brought to you by Moneyweb

For more news your way

Download our app and read this and other great stories on the move. Available for Android and iOS.

Published by
By Moneyweb
Read more on these topics: EskomRolling blackouts