Eastern Cape lost R338 million housing budget to other provinces

Published by
By News24 Wire

The Eastern Cape human settlements department failed to spend R338 million allocated for housing developments in the past financial year.

The money was then taken and re-allocated to other provinces.

Human Settlements Minister Lindiwe Sisulu revealed this during her budget vote speech in the National Council of Provinces (NCOP) in Cape Town on Friday.

ALSO READ: Municipalities owe R12bn in unpaid water bills – Sisulu

This is even though there are 115 townships in the Eastern Cape which had been earmarked for upgrades.

The two metros in the province, Buffalo City in East London and Nelson Mandela Bay in Gqeberha, also have a further 43 and 8 townships earmarked for upgrades.

Sisulu revealed that the Eastern Cape is one of four provinces that failed to spend, followed by the Free State and North West with R100 million each and Limpopo with R50 million.

Sisulu said the funds blocked from the four provinces were diverted to Gauteng, Mpumalanga, Northern Cape, and Western Cape.

Sisulu said she invoked section 18 and 19 of the 2020 division of the Revenue Act and blocked the funds from the provinces after they had difficulties in spending it.

She said the move came after she had had several meetings with MECs of the provincial departments where there were discussions about their recovery plans.

Contacted for comment, the Eastern Cape human settlements department blamed Covid-19 for the underspending.

The head of the department Tabisa Poswa said: “The full lockdown between March 2020 to June 2020 impacted on all contractor’s performance.

“The Covid-19 pandemic in the 2020/2021 financial year was, as is well known, devastating for many small businesses in that many contractors struggled for a significant time after June 2020 to re-establish on site (work) due to the restrictions on their operations, a lack of human resources, a shortage of material supplies, and the onerous health and safety requirements of the pandemic.”

She said the turnaround time for the delivery of building materials was significantly prolonged, which in turn affected the performance of the contractors on site.

“During June 2020 at the end of second quarter of the financial year, the Department was not able to meet the targets on key performance areas and underspent due to the slow reestablishment on site by contractors and their ability to regain their human resources back on site and the impact of the new Covid Regulations on the contractors to re-establish (work on) site,” said Poswa.

She also revealed that the money that was blocked was meant for projects in Nelson Mandela Bay Metro and Amathole District Municipality. There was also shortage of material supply because the manufacturers were also closed and all these industries were impacted by the new COVID regulations on occupational, health and safety requirements. Turn-around time for material delivery was significantly increased, resulting in slower performance on sites.- Eastern human settlements department HOD Tabisa Poswa.

Poswa said despite the difficult situation presented by lockdown, over 70% of the budget was used and can be accounted for.

She said out of 6 807 houses which were targeted for construction, the department managed to build 5 338 houses.

Malibongwe Dayimani

For more news your way