Business

Still some way to go for R6bn Karpowership deal, but must dock by 2025

Published by
By Vukosi Maluleke

Controversial energy producer Karpowership has been granted environmental authorisation for the development of a 450MW gas to electricity power plant, but still has some hoops to jump through.

The R6 billion project is earmarked for the Port of Richards Bay, with construction required to conclude within two years of granting the environmental permit. 

While Karpowership said the next step would entail finalising agreements with Transnet National Ports Authority (TNPA), an approval notice seen by The Citizen stipulates the company must conduct a 12-month pre-construction environmental observation. 

Advertisement

ALSO READ: Karpowership gets green light in bid to hit the waters

Long road ahead

The Department of Forestry, Fisheries and the Environment identified critical biodiversity areas in the project.

Karpowership’s construction site is located less than a kilometre away from the Richards Bay Nature Reserve and 10 kilometres from the Enseleni Nature Reserve.

Advertisement

This requires careful observation and planning to minimise impact, especially since the gas pipeline will contain about 30 to 80 cubic metres of LNG at any given time. 

Karpowership is set to clear at least one hectare of indigenous vegetation to make way for a switching station and temporary construction facilities.

Built on shore, the switching station will serve as a connection point between the Powership and Eskom’s national grid.

Advertisement

The environmental permit also requires Karpowership to development facilities for the storage and handling of dangerous goods.

Another notable task ahead entails developing infrastructure for the bulk transportation of gas through pipelines which can deliver a throughput capacity of more than 700 tons daily. 

ALSO READ: Expert calls on govt ‘to come clean’ on controversial Karpowership deal

Advertisement

Karpowership is required to meet conditions within two years of issuing of authorisation. 

“If the commencement of the activity doesn’t occur within that period, the authorisation lapses,” it noted, further stipulating that a new application would have to be made.

ALSO READ: Karpowerships: Contract could be reduced to 10 or 5 years

Advertisement

Welcoming the green light

Karpowership SA welcomed the environmental authorisation, adding R6 billion has been set aside for the project.

“Karpowership SA is proud to be able to play a significant role with its state-of-the-art LNG to Power technology in Richards Bay, assisting South Africa in achieving its net-zero targets,” it told The Citizen.

ALSO READ: Karpowership donates game farm to wildlife body amid power plant plans

For more news your way

Download our app and read this and other great stories on the move. Available for Android and iOS.

Published by
By Vukosi Maluleke
Read more on these topics: ElectricityEskomKarpowershipLoad Shedding