Negligence behind costly Medupi explosion, DPE tells Parliament

The Department of Public Enterprises (DPE) has confirmed that preliminary investigations into the explosion at Eskom’s Medupi Power Station indicate that the incident was a result of standard procedures not being followed.

DPE director-general Kgathatso Tlhakudi briefed Parliament’s portfolio committee on public enterprises on Wednesday morning, where he gave an update on the Medupi unit 4 explosion that occurred on 8 August.

Purging

The explosion took place at the coal-fired power plant near Lephalale in Limpopo just before 11pm on the day while hydrogen was being displaced with carbon dioxide and air, in order to find an external leak. 

Advertisement

This procedure of displacing hydrogen with carbon dioxide and air is called purging.

After the explosion, which took place while the unit was on a short-term outage, it was found that while employees were finding the leak, there was still hydrogen in the generator, which created “an explosive mixture”.

ALSO READ: Medupi: ‘Paper milestone’ doesn’t address cost, tech, environmental failures

Advertisement

This ignited, and resulted in the explosion. The explosion resulted in extensive damage to the generator and other components within close proximity.

Eskom’s operating department was tasked with the purging of hydrogen from the generator prior to the leak search.

The incident took place just one week after Eskom declared that the contentious Medupi plant had finally reached commercial operation status. 

Advertisement

Procedures not properly followed

During the briefing, Tlhakudi told the committee that the full extent of the damage is still to be determined, adding that investigations currently point to negligence being behind the explosion.

“What has been determined is that the procedures in terms of purging were not properly followed. Those that oversaw that operation have been suspended [until] the proper investigations are confirmed,” the director-general said.

The suspended employees include an operating manager, an outage manager, two shift managers and four senior plant operators.

Advertisement

Eskom previously indicated that the employees were suspended, among other reasons, because it believes there was “a deviation from the procedure for carrying out this activity”.

READ MORE: Eskom not honest about Medupi power plant, claims DA

Meanwhile, Tlhakudi further said that an inspector of machinery has since completed the site inspection, while a recovery manager has also been appointed.

Advertisement

“The inspector has been on site and she is doing her own investigation. Rotek [Industries] which is a part of Eskom is also doing some work in order to un-assemble [the plant] to assess the damage caused,” he said.

The director-general also confirmed that the original equipment manufacturer (OEM) has been involved in the effort to repair the unit and return it to service.

Costs

Eskom CEO André de Ruyter recently told News24 that the explosion could add up to R2 billion to the extensive power plant’s bill, and could take up to two years to mend. 

The results of an investigation are not yet complete, which means it could cost even more money. 

There was talk of taking unit six of the Kusile Power Station and moving it to Medupi, independent energy expert Chris Yelland told Moneyweb.

ALSO READ: Medupi explosion may not mean more load shedding, but will cost Eskom billions

However, nothing had been confirmed yet. This would save time, but it could potentially cost Eskom more than ordering a new generator and installing it, he said.

The reason a generator takes time to be replaced is because it is a bespoke design specifically made for the Medupi project.

It also has to be shipped from France.

Additional reporting by Sipho Mabena and Nica Richards

For more news your way

Download our app and read this and other great stories on the move. Available for Android and iOS.

Published by
By Molefe Seeletsa
Read more on these topics: business newsEskomMedupi Power Station