It appears the R2.5 billion penalty that Eskom imposed on Optimum Coal Mine – and which is controlled by Gupta-owned Tegeta Resources – has been settled via arbitration with Eskom.
Jacob Zuma’s son, Duduzane, is the other shareholder in Tegeta.
The arbitration process appeared to have moved very quickly. Moneyweb asked for an update on March 8 2017. Eskom spokesperson Khula Phasiwe replied: “The matter will be going for arbitration soon. The nitty-gritties will be announced at a later stage.”
When we followed up on April 6 2017 (last Thursday) Phasiwe informed us: “The arbitration is private and we are bound by the rules of confidentiality. Details cannot be divulged but the arbitrator has made an award.”
When we asked what the award amounted to, or what the details of the arbitration were, we received no response from Eskom. Similarly, when we put the question of what progress had been made on the matter to the Gupta’s PR company, Bell Pottinger, we received no response.
The original penalty imposed by Eskom on Optimum at the time Glencore owned it was R2.5 billion. Tegeta took financial control of Optimum on January 1 2016, with the deal eventually closing in April, when Eskom supplied the company with R586 million to assist with payment of the R2.15 billion purchase price. (The penalty was greater than the purchase price.)
We warned back in April last year that this deal would be the litmus test to see whether the relationship between the Guptas and Eskom, and by default, the South African government, was fundamentally corrupt – given the financial terms of the deal. It seemed illogical for Tegeta to pay a purchase price and accept liabilities that together amounted to some R8.45 billion without undertaking any due diligence.
This was a penalty Eskom was adamant it was going to hold Optimum to. Phasiwe said a year ago, when Optimum was still being managed by the business rescue practitioners: “Before Optimum went into business rescue, we imposed the penalty, but once it entered business rescue it was ‘parked’ or suspended. The business rescue practitioners then struck a deal with Tegeta Resources, where they would take over the penalty and all other items relating to the contract. So we are not waiving the penalty, and Optimum must still deliver on the volume, price and quality as stipulated in the contract until 2018 for the supply of coal to the Hendrina Power Station.”
Moneyweb will be pursuing legal avenues to obtain details of the settlement.