Load shedding schedule for stage 2 and stage 4
Load shedding shifts from stage 2 to stage 4
The Emalahleni Local Municipality announce that Eskom will reduce load shedding to Stage 2 from midnight until 05:00 today.
Load shedding Stage 4 will then be implemented from 05:00 until 00:00.
The following substations will be affected as follows:
Stage 2:
Clewer, Ogies and Phola Substation will be affected from 01:00 until 03:30.
Stage 4:
Grobler Substation will be affected from 05:00 until 07:30.
Buffer Substation will be affected from 07:00 until 09:30.
Doornpoort, Rietspruit, KwaGuqa, Clewer, Ogies and Phola Substation will be affected from 09:00 until 11:30.
Ga-Nala Substation will be affected from 11:00 until 13:30.
Grobler Substation will be affected from 13:00 until 15:30.
Buffer Substation will be affected from 15:00 until 17:30.
Clewer, Ogies and Phola Substation will be affected from 17:00 until 19:30.
Ga-Nala and KwaGuqa Substation will be affected from 19:00 until 21:30.
Grobler Substation will be affected from 21:00 until 23:30.
Buffer Substation will be affected from 23:00 until 00:00.
More information can be found on the Emalahleni Local Municipality’s Facebook page.
Share your news tips via:
Telephone: 013 656 2490 WhatsApp: 060 866 8682 Email: info@witbanknews.co.za
Or follow us on WITBANK NEWS platforms:
Instagram, Twitter Witbank News App Facebook page Witbank News Breaking