Planned power outage schedule 8-11 September

The municipality will be embarking on a maintenance and repair program on distribution transformers.

The schedule is as follows:

Ringsub 4 substation – Monday 8 September
From 08:30 TO 16:30

The Following areas will be affected:
•KwaGuqa Ext. 4 & 5

Ringsub 3 substation – Tuesday 9 September
From 08:30 to 16:30

The following areas will be affected:
•KwaGuqa Ext. 10, 7, 9, 11 & 18
•KwaGuqa Ext. 10 RDP

Buffer substation – Wednesday 10 September
From 08:30 to 16:30

The following areas will be affected:
•Ferrobank 6,6kV network (Industrial area)

Point B substation – Thursday 11 September
From 08:30 to 16:30

The following areas will be affected:
•Del Judor Proper (Part thereof – area of and Engen Garage)
•Witbank Ext. 8 (Part thereof)
•Witbank Ext. 5
•Point B 6,6kV Pumpstation

Please be patient should the power not be restored according to the schedule.