Layover facility opposite Itsoseng is 90% complete

The construction of the layover facility opposite Itsoseng/Goseame falls under the Leeto la Polokwane initiative, an integrated public transport system and is part of the preparation for the system to start operations.

POLOWKANE – The layover facility opposite Itsoseng, is a step closer to being complete.

The construction of the layover facility opposite Itsoseng/Goseame falls under the Leeto la Polokwane initiative, an integrated public transport system and is part of the preparation for the system to start operations.

Read more: Leeto la Polokwane the journey begins

Leeto la Polokwane, an integrated public transport system aimed at providing the city with public transport that is safer, faster, affordable, efficient and environmentally friendly, is in line with the national policy to transform the public transport sector through the provision of a high-quality transport system.

The facility will accommodate buses during off-peak periods. The construction of the facility started in July 2018 and it was initially projected that it would take six months to complete, according to the municipality. The project suffered delays at the time, with the contractors’ break from December 2018 to January 2019 being a factor.

At the time, Manthlako Sebaka, Transport Marketing, Communications and Stakeholder Relations Managerfor Leeto la Polokwane, said that despite the contractor being behind schedule, the municipality received a catch-up plan. The delays would also have financial implications for taxpayer, however, it now has a negative impact in the sense that the facility is not in use yet.

The projection of the completion date with the implementation of the catch-up plan was 30 June. According to Sebaka, the facility is currently at 90% complete.

“The fencing is complete, paving was done and the office will be completed within a month. It will come into use once the operation begins,” he said.

reporter04@nmgroup.co.za

For more breaking news follow us on Facebook Twitter Instagram or send us a message on WhatsApp 079 418 4404

At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!
You can read the full story on our App. Download it here.

Related Articles

Back to top button