Berario, Fairland, Northcliff, Blackheath, Emmarentia and surrounding areas were affected by a power outage this morning, 3 August.
The spokesperson for City Power, Sol Masolo, expects the power to be restored within six hours, with power likely to be restored by 4pm this afternoon.
MUST READ: substation’s R110 million upgrade underway
“One of the circuit breakers at Roosevelt [Park] Substation blew up this morning causing power interruption that affected the areas,” Masolo said.
He explained that technicians are busy with repairs onsite.
Related articles:
City Power outages soon to be a thing of the past
City reverses cancellation of City Power Lifeline Tariff