N4 Kaapmuiden interchange upgrade progressing well

The project is being completed by Tau Pele Construction and will see this 15.5km stretch of the carriageway upgraded to four lanes and will also include the rehabilitation of the current road.

There has been significant progress in the upgrade and rehabilitation project between Kaapmuiden and the Kaalrug Intersection.

The project got off the ground in August this year and 5% has already been completed. The project is being completed by Tau Pele Construction and will see this 15.5km stretch of the carriageway upgraded to four lanes and will also include the rehabilitation of the current road.

READ: Karino Interchange expected to ease traffic flow

“The installation of high mast streetlights at the Kruger Malelane Gate/Jeppes Reef Interchange and a footpath between Stentor and Kaapmuiden Primary School are only some of the specific safety issues raised by the Nkomazi Local Municipality that will be addressed in the project,” said TRAC.

ALSO READ: More roadworks planned for N4 this year

Approximately R340-million has been budgeted for the project and is expected to take 24 months to complete. Road users are advised that traffic flow will be affected throughout the roadworks as lane reductions and deviations will be in effect.