The Johannesburg Roads Agency has announced that the reconstruction of four streets in Mayibuye would be complete by June, this year.
The streets, which include Lebowa, Mankgagane1, Mankgagane 2 and Xinimbela streets were identified for reconstruction following the completion of a Road Visual Condition Index.
“The index programme enables the scientific prioritisation of roads for reconstruction and resurfacing city-wide. Resurfacing and reconstruction of roads remains the long-term solution to improving the condition of Johannesburg’s 13 428km road network,” said JRA spokesperson Bertha Peters-Scheepers.
Read JRA speaks out about Crowthorne’s Arthur road constructions.
The project, which commenced in September 2015, includes the building of new stormwater drainage systems. It covers 1.9km of road, with a R20 million budget.
Edited by Beryl Knipe
What do you think of the City’s roads rehabilitation project? Tweet us on @MidrandReporter