Last night Eskom confirmed that it commenced with stage 1 load shedding.
Eskom spokesperson Khulu Phasiwe said, “The load shedding was caused by intimidation and acts of sabotage earlier in the day.”
#Power_Alert: Load shedding commenced at 11:29 and will continue until 21:00. Schedules available on @Eskom_SA https://t.co/S9zcC9bSYJ or local municipalities if you are a municipal customer. Customers are cautioned to treat all electrical connections as live during this period.
— Eskom Hld SOC Ltd (@Eskom_SA) June 15, 2018
Ekurhuleni Load Shedding Schedules
Click on the image to enlarge and download to your device or select the relevant link below for the PDF version. Keep these for later use.
PLEASE NOTE: Should there be load shedding the City of Ekurhuleni (CoE) will make use of the 2014 schedules.
Edenvale 2014 LoadsheddingEdenvale Bedfordview
Bedfordview 2014 LoadsheddingEdenvale Bedfordview
Germiston 2014 Loadshedding Germiston Palm Ridge
Kempton Park 2014 Loadshedding Kempton Park Esselen Park
Power consumption can be lowered by switching off geysers, pool pumps, heaters and non-essential appliances in the peak period between five in the afternoon and eight in the evening.
Electricity has been restored in all areas.@Eskom_SA would like to thank you for helping us keeping the power system stable.
Please continue to use electricity sparingly and to switch off non-essential appliances.@Eskom_SA apologises for any inconvenience caused.
— Eskom Hld SOC Ltd (@Eskom_SA) June 14, 2018